Starting the Repairs

6th August – today the scaffolding appears to be almost complete on the South Pavilion.

A large lorry arrived at lunchtime from Ducker and Young Ltd scaffolding contractors to deliver further scaffolding poles and brackets. They are also delivering a collection of stone so that as soon as the scaffolding is complete, work can begin to repair and clean the damaged stonework on the south pavilion.










Who Else Has Been Involved In The Project?

Howard Benge, Regional Learning and Interpretation Officer for the Thames and Solent region says:

I’m really happy to see the stone work exhibition open. It's funny to see it in a finished state, after talking about it and planning it for so long. When I had my first look round, a volunteer pointed out a before and after photograph in the panels. I’d never seen this before. One of pictures shows the columns in their splendid entirety. This is the old photograph. A recent picture shows one of the columns with a huge chunk taken out of the capital. This damage spurred on the stonework project. When you are looking round, see if you can spot that.

I’m looking forward to the exhibition changing with the Stonework project over the course of the next year.

Tuesday, 4 August 2009

Weeks 2 and 3, scaffolding work begins




28th July, scaffolders arrive on site and begin erecting the scaffolding around the South Pavilion








28th July, a cherry picker was used for two days to establish the extent of the work to be done on the North Pavilion



3rd August, the scaffolding on the South Pavilion is almost complete. When the scaffolding is fully erected, the fencing will be removed, leaving the green boardings as protection.

Friday, 17 July 2009

Week 1 - Project Start

On Monday 13th July the project contractors, Ward & Co. arrived on site and began to build their compound near to the mansion.Power Electrics lorry delivering the large generator within a container to the compound at Basildon Park
Power Electrics delivered a large generator on Day 1 of the project.

One of three large containers being delivered outside the mansion, to be used as a work site office space The large container being transfered from the lorry to the compound space by hiab (lorry crane) The second container being put in place - Only a portable toilet is left on the truck to be unloaded.
On Tuesday delivery was taken of the temporary office and staff-room for Ward & Co. which are to be located in the compound.


Next week, starting 20th July, the scaffolding design will be complete and the building of the scaffold around the house will begin.

So far this week the stonework exhibition has proven popular with our visitors who are interested to learn more - By far the most popular part of the exhibition is the "Build Your Own Palladian Mansion" model with both adults and children enjoying the task!











Wednesday, 15 July 2009

Preparing the exhibition space

For over 6 months a team of property and regional staff have been working towards putting together an exhibition space for the stonework project. This is to be housed in the South Pavilion Conservatory, Drawing Room and Dining Room - none of which have been opened to the public before.

This picture shows the conservatory before the children's activities were put in place.

The exhibition gives a chance to learn more about the stonework project at Basildon Park, the history and architect of Basildon Park and nature conservation on a project like this. We have a childrens activity area housed in the Conservatory, a reading room located in the Dining Room and the main exhibition boards in the Drawing Room.

The rooms are presented as they were left to the Trust and still require a lot of work - Income from raffle tickets sold in 2009 will go towards caring for the South Pavilion in the future.


Laura Weatherall, House Steward at Greys Court
Measuring the interpretation panels to be attached to the main boards.

Thursday, 11 June 2009

Basildon Park Stonework Project Update

The stonework project has been delayed slightly and is now due to begin on Monday 13th July.

The team have been very busy getting the stonework exhibtion ready. It gives lots of information on the project including interactive activites and dressing up options for children. There will also be a reading area available to visitors. The exhibition is to be housed in the Drawing Room and Dining Room of the South Pavilion. Having only recently been taken in-hand by the Trust, this will be an exciting new space to discover for both new and frequent visitors.

Visit us regularly to see how the project progresses!

The parkland to the west front of Basildon Park

Thursday, 9 April 2009

Problem Photos

Front facade of Basildon Park, stone discoloured on sides of ionic columns and pediment, crumbling on columns and lichens growing

These photographs show the effects of time, weather and organisms on the stonework at Basildon Park. In many places the stone is discoloured and crumbling. You can see yellow Lichen - a fungus that lives on the stone, in many places.

Lichens growing on the stone portico - appear as yellow moss Pediment at front of Basildon Park, discoloured by weather over a period of time







South Pavillion, large chunks of stone missing around windows