I.J.P. (stonemasons) will:
· carry out a second wash on the main house.
· carry mortar samples and copperas.
· continue pinning back the loose stone on the cleaned areas.
· continue with the mortar repairs
Ward and Co. will continue to work on the window repairs
Everest Roofing will continue work on the roof
The glazier will continue work on the windows
Monday, 23 November 2009
Monday, 9 November 2009
Work program for week beginning 9/11/09
The stonemasons will continue work cleaning the main house moving around the building in an anti clockwise direction. At the moment they are on elevation 8. They will apply the bio-algo-cide to west elevation but not in the portico.
They will conduct a cleaning trial in the portico using water to establish if dirt can be removed without affecting the copperas and will continue pinning back the loose stone on the elevations previously cleaned on the south pavilion and the main house.
Mortar repairs will be carried out using an agreed palette of mixes and pointing of the stone work on the south pavilion and the house will be carried out.