Pre-Christmas:
- I.J.P. will continue with the cleaning and mortar repairs on the south pavilion and the main house.
- Bowden & Ward will continue to fit the new stone on the south pavilion and the main house.
- Everest roofing will finish the roof work by Wednesday.
- The decorators will paint the windows concentrating on the south pavilion first floor and working their way down.
- Ward & Co. will continue with the window repairs finishing the south pavilion.
Post-Christmas:
The scaffolding, site, window protections and frost protections will be inspected and any maintenance carried out.
- I.J.P. will continue with the mortar work on the south pavilion and the main house.
- Bowden & Ward will continue with the stone replacement to the south pavilion and the main house.
- The decorators will continue to paint the windows, concentrating on the south pavilion then moving on to the main house.
- N.C.A. will review the lead work with the lead worker from Everest.
- Ward & Co. will continue to repairs to the windows on the south pavilion and the main house.